SiteworkMath — cubic-yard markConstruction math from people who’ve thrown the wheelbarrow.
Tools · Project planningNew construction · Feasibility

New construction cost calculator — the budget I’d use before I close on the lot.

Plug in the square footage, set the quality + location + complexity, flip the management toggle. The output is a feasibility budget — not a contractor bid. The number I’d use to decide whether to close on the lot, walk away, or counter-offer the seller.

sqft
Gross floor area of the conditioned envelope, finished + unfinished rolled together.
Standard = rental finishes; high = custom + slab counters.
Chicago metro is mid; Bay Area + NYC are high.
Moving load-bearing walls or stairs flips simple → complex.
Management
Line item
Range (low — high)
% hard
Confidence
Design + drawingssoft
$6,560$9,440(mid $8,000)
Medium
Permits + feessoft
$3,400$6,600(mid $5,000)
Rough
▸ Operator note

Permit fees on a new-build vary a lot by township — every municipality sets its own. The fee isn't the issue; the calendar is. Typical timing: • Fast jurisdiction: ~2-4 weeks • Typical: 5-8 weeks • Strict, with a structural-review cycle: 12-16 weeks Every week sitting in plan review is interest you're paying on the construction loan without a stud raised.

Site prep + utilities
$8,160$16K(mid $12K)
5.0%
Rough
▸ Operator note

Site prep is where new-builds blow their first contingency. Three common surprises: • Soil borings come back worse than the lot listing implied • The existing utility tap is 80 feet from where the architect drew it • The curb cut you assumed was free actually needs its own permit Don't skip the soils report — a $2K test in due diligence beats a $25K helical-pier surprise after foundation is poured.

$21K$31K(mid $26K)
10.9%
Medium
▸ Operator note

Foundation on a new-build is full-scope: frost-line footings, foundation walls, plus a slab or basement floor depending on the region. Below-grade work uses the concrete-yardage calc for the ready-mix order. The trap on rolling lots: footings come back wrong more often than they should. Confirm the surveyor's elevations before the forms go in, not after the inspector flags it.

Framing + structural
Refine later when framing calc ships
$30K$42K(mid $36K)
15.1%
Medium
Roofing + envelope (windows, siding)
$25K$35K(mid $30K)
12.6%
Medium
▸ Operator note

Envelope is where the energy bill is decided for the next 30 years. Tier defaults: • Standard: regular asphalt shingle, vinyl siding, builder-grade windows • High: architectural shingle, fiber cement (paint-grade siding that doesn't rot), double-pane low-E argon glass Don't pay for high-tier envelope on a spec build whose comps won't justify it — but don't cheap out on flashing details either. The buyer who walks the inspection asks about the roof age, not the siding profile.

Electrical (full new service)
Refine later when electrical calc ships
$13K$19K(mid $16K)
6.7%
Medium
Plumbing (full new system)
Refine later when plumbing calc ships
$16K$24K(mid $20K)
8.4%
Medium
HVAC (system + ductwork)
Refine later when HVAC calc ships
$11K$17K(mid $14K)
5.9%
Medium
Insulation
$2,700$3,300(mid $3,000)
1.3%
High
▸ Operator note

Insulation is the homeowner-DIY line on a new-build too. Batt and roll insulation in stud bays is the easiest install on the project — owner-builders save the labor here ($1-2/sqft) and just buy the materials. Spray foam still needs a pro and a respirator. On a new-build the cavities are clean and accessible, so DIY savings are real if you have the time.

Drywall (hang + finish)
$12K$18K(mid $15K)
6.3%
Medium
▸ Operator note

Drywall pricing splits into scope tiers — what you pay per 4×8 sheet depends heavily on which scope is in the quote. Chicago metro 2024: • Hang-only labor (no finishing): $25-$45 per sheet • Hang + tape (light finish, not paint-ready): $35-$65 per sheet • Full Level 4 (hung, taped, mudded, sanded, paint-ready): $50-$90 per sheet • Level 5 (skim-coat smooth, kitchens + baths under recessed cans): $75-$120 per sheet Anchored on Fixr's $1.50-$3.50 per sqft of finished wall surface plus BLS labor inflation of roughly 25-30% since 2019. The engine's drywall baseline is calibrated to full Level 4 with finishing labor included — pay for Level 5 in kitchens and baths because every imperfection shows under the lights.

Paint + flooring + tile
Refine with Tile calc (partial)
$18K$26K(mid $22K)
9.2%
Medium
Kitchen + bath finishes
$18K$34K(mid $26K)
10.9%
Rough
▸ Operator note

Highest-variance line on a new-build, same as on a gut. This is a PLANNING-RANGE FINISHES ALLOWANCE, not a true cap. Industry benchmarks (HomeAdvisor / This Old House / Fixr 2024): • Single full bath: $10K standard / $17K midrange / $30K+ luxury • Major kitchen: $15K / $35K / $80K+ The calc's quality multiplier (1.0×/1.3×/1.7×) is narrow on purpose — it sizes a baseline 1-kitchen-plus-2-bath package and won't reach true custom millwork or primary-suite scope. Use the override field whenever scope is known — luxury new-builds, primary suites, or extra bathrooms all need a direct override. Counter template and fab is a hard 2-week lead time. Order cabinets the day permits clear.

$6,800$13K(mid $10K)
4.2%
Rough
Appliances
$7,200$8,800(mid $8,000)
3.4%
High
Contingency reservecomputed
$19K$43K(1015% hard)
▸ Operator note

Contingency is what you draw from when the basement floods at week 4 or the inspector shows up with a punch list five lines longer than expected. How it scales: • Base: 12% on a clean property • Each leak-check flag adds 1.5% (capped at 22%) If your contingency band is below 10%, the deal isn't there yet — walk the property with a contractor before tightening.

GC overhead + profitcomputed
$19K$43K(1015% hard)
▸ Operator note

GC overhead and profit runs 10-15% on hard costs for residential GCs in the Chicago metro — covers the job-site supervisor, scheduling, insurance, and the GC's margin. Two things this is NOT: • NAHB's 16.7% figure is on SALE PRICE, a different calculation that includes builder profit on the resale. • Owner-builder mode drops this line entirely — but adds a 1.26× slowdown to the timeline (Census 2024: owner-built homes average 15.2 months vs 12.1 months contractor-built).

Feasibility budget

Feasibility budget: $237K–$389K

Not a contractor bid. The budget I'd use to decide whether to walk, bid, or kill.

$119–$194/sqft total · 2,000 sqft · GC managed

Hard costs
$189K — $287K
mid $238K
Soft costs (design + permits)
$10K — $16K
mid $13K
Contingency reserve (10–15%)
$19K — $43K
mid $29K
GC overhead + profit (10–15%)
$19K — $43K
mid $30K
Total feasibility budget
$237K — $389K
mid $309K
What raised the contingency band
  • Base contingency 12% on a clean property — no leak-check flags raised.
Budget cushion
The math (mid estimate)$309K mid · hard + soft + contingency + GC overhead
What I’d actually need before startingDon’t start under $390K liquid+ ~$48K reserve in case of a leak-flag surprise
Why the cushionOn a gut rehab the walls don't tell you what's behind them until demo. The math gives you a mid; the cushion is what you draw from when the inspector finds knob-and-tube on a 1920s bungalow you bid on the photo set.
When NOT to over-padIf you're stretching to make the high-band fit, you're flagging that the deal isn't there. Walk the property with a contractor before tightening — don't pretend better discipline closes a deal that doesn't pencil.
Top cost drivers

Five lines that drive most of the hard-cost stack on this property. Override one of these and the feasibility budget moves.

  1. Framing + structural$36K mid · 15.1% of hard
  2. Roofing + envelope (windows, siding)$30K mid · 12.6% of hard
  3. Foundation + slab$26K mid · 10.9% of hard
  4. Kitchen + bath finishes$26K mid · 10.9% of hard
  5. Paint + flooring + tile$22K mid · 9.2% of hard
Refine this estimate

Drop into a detail calc to tighten one of the lines, then come back and override the value.

Ask a SiteworkMath question

Quick answers about SiteworkMath's calculators and material take-offs — concrete yardage, topsoil + mulch volume, tile box-count, deck-surface materials. Free, no signup. Not structural-engineering or code advice — for joist / beam / footing / permit decisions, talk to a structural engineer, licensed contractor, or your local building department.

Hi, I'm the SiteworkMath assistant. I answer questions about the calculators and guides on this site — concrete yardage, topsoil, mulch, tile, and decking material math. I'm not a structural engineer or a licensed contractor; I'm a calculator built around the math that James Wu — Chicago-area flipper — uses on his own jobs. For structural decisions (joist sizing, beam spans, footing depth in your soil + climate, anything that needs a permit) talk to a licensed structural engineer or your local building department.

How I’d actually use this on a new-build

New-build pencils differently from gut rehab. On a gut, the cost surprises hide behind walls. On a new-build, the cost surprises hide in the dirt. I run this calc twice: once before I make an offer on the lot (lot price + this output should fit comfortably inside ARV minus 20% for new-build profit margin), and once after the soils report comes back. The soils report is what tells you whether the foundation line is honest. If the borings come back with poor bearing capacity or expansive clay, override the foundation line up by 30–50% before re-running the math.

The owner-builder toggle is the question that gets asked most on new-build. The math says “save the GC markup,” but the calendar tells the truer story. Census 2024 puts the slowdown at 1.26x — three extra months on a new single-family build, or about 90 days of extra construction-loan interest at residential rates. On a $400K loan at 8.5%, that’s roughly $8,500 in extra interest before you save a single dollar on markup. The cost calc shows the dollar gap between GC and OB; the timeline calc next door shows the calendar gap. Run both before deciding.

On Chicago-metro new-builds I’ve walked, the lines that consistently surprise are site-prep (utility taps that turn out to be 80 feet from where the architect drew them, curb cuts that require a separate permit), foundation (rolling lots where the surveyor’s elevations and the engineer’s footing schedule don’t agree until concrete is being poured), and kitchen-bath finishes (counter-fab is a hard 2-week lead time regardless of how fast the install crew moves — order cabinets the day permits clear or eat the lead time at the wrong end of the project). The operator notes on those three lines reflect exactly that pattern.

Where the new-build budget actually breaks

Five places the new-build budget lies to operators who haven’t built before:

Methodology

Every dollar number on this page traces to one of three layers: NAHB 2024 Cost-of-Constructing-a-Home survey ($162.50/sqft average, used as a per-sqft sanity check), HomeAdvisor / Fixr / Angi cross-checks for line-level baselines, and Chicago-metro builder experience for the operator notes and confidence labels. The full per-cluster sourcing tier in methodology spells out which sources back which kinds of claims. The numbers are planning ranges, not contractor bids — the feasibility caveat is part of the engine output for a reason.

Show the formulas
  • Per line: perSqftMid × sqft × locationMult × complexityMult × qualityMult = engine mid. Override (if set) replaces the engine mid; band still derives from confidence. Rehab-only leak-flag deltas are n/a on new-build because new-construction line items don’t declare them.
  • Quality multiplier:standard 1.0× (rental / spec build) / mid 1.3× (move-in / owner) / high 1.7× (custom / luxury). Per-line response factor (full / partial / none) determines how much applies — finishes scale full; site-prep and foundation don’t scale.
  • Location multiplier: low cost 0.85× (Midwest exurb) / mid 1.0× (Chicago metro anchor) / high 1.25× (HCOL coastal).
  • Complexity multiplier: simple 0.92× / moderate 1.0× / complex 1.18×.
  • Contingency:12% baseline on hard mid, capped at 22%. New-build doesn’t expose the rehab leak flags — but if a strict-permit-jurisdiction flag fires from the input row, contingency escalates +1.5% per active flag.
  • GC overhead + profit:12.5% mid on hard mid (low 10% / high 15%). GC mode only — Owner-builder drops the line. Anchored on Chicago-metro residential GC industry typical, NOT NAHB’s 16.7% sale-price figure (which is a different calculation including builder profit on resale).
  • NAHB 2024 anchor: $162.50/sqft average used as a sanity check on the per-sqft total. SiteworkMath default standard 2000sqft mid lands at ~$157/sqft, just below the NAHB average — defensible for a low-end spec build in Chicago metro.
  • Engine logic: lib/sitework/projectcost/projectcost.ts with line catalog in line-items-newbuild.ts and types in types.ts. Tested in projectcost.test.ts.

Frequently asked

What does this new construction cost calculator actually estimate?

A planning-range feasibility budget for a residential new-build single-family home — the dollar number an operator uses to decide whether the lot + build pencils before calling builders. Not a contractor bid. The engine sums 14 line items (design, permits, site-prep, foundation, framing, envelope, electrical, plumbing, HVAC, insulation/drywall, paint/flooring/tile, kitchen/bath, exterior/landscaping, appliances) plus computed contingency and (in GC mode) overhead. Numbers are SiteworkMath planning ranges anchored on NAHB 2024 Cost-of-Constructing-a-Home survey, HomeAdvisor / Fixr / Angi cross-checks, and Chicago-metro residential-builder experience.

How does this differ from the gut rehab cost calculator?

Same engine, different line-item baselines and framing. New-build adds a site-prep phase (excavation + utility tap + grading) where gut-rehab has demolition + disposal; new-build always includes foundation work where gut-rehab leaves it as an opt-in flag; and new-build's framing + envelope baselines reflect full-scope work from scratch instead of partial repair. The Rehab Leak Check property-flag panel is hidden on new-build (no existing structure means no buried-wall surprises) — the strict-permit-jurisdiction risk is captured in the existing input row instead. Default 2000-sqft standard / mid / moderate runs about $315K total mid (~$157/sqft), in line with NAHB 2024's $162.50/sqft average.

Why is NAHB used as a sanity check, not a constructive multiplier?

NAHB's annual Cost-of-Constructing-a-Home survey publishes one nationwide average ($162.50/sqft for 2024 — that's an average across surveyed builders, not a Census median) and an 8-stage breakdown of where the dollars land (site work / foundations / framing / exterior finishes / major systems / interior finishes / final steps / other). Those breakdown percentages are useful for sanity-checking a bottom-up estimate, but they're aggregated across regions and quality tiers, so plugging them into a Chicago-metro mid-quality calc as a multiplier would import noise from very different markets. SiteworkMath uses NAHB to confirm the per-sqft total looks sane (~$157 standard / ~$186 mid / ~$216 high at default location), not to derive it. NAHB's separate 16.7% builder profit-on-sale-price figure is a different calculation from SiteworkMath's GC overhead 10–15% on hard costs — see methodology for the disambiguation.

What's the difference between GC-managed and Owner-builder mode on a new-build?

GC-managed adds 10–15% on hard costs as overhead and profit (mid 12.5% — Chicago-metro residential GC industry typical). Owner-builder drops that line entirely. The trade is calendar: per Census 2024, owner-built single-family construction averages 15.2 months vs 12.1 months for contractor-built — a 1.26x slowdown. The construction timeline calculator surfaces the calendar delta directly; this calc only shows the dollar delta. Most operators who think they're saving the markup on a new-build are actually trading dollars for calendar — and the construction loan eats interest on every extra month.

What's NOT included in this calculator's output?

The lot. Site work assumes a buildable lot is already acquired and the title is clean — lot acquisition + closing costs + impact fees + any environmental remediation are scope for a separate budget. Specialty items (pool, accessory dwelling unit, detached garage at high-end finish, custom millwork above the kitchen-bath-finishes baseline) aren't captured by the 14-line catalog at this resolution; bump the kitchen-bath-finishes line via override or step up to a contractor walk-through for those. Contractor profit on the resale (NAHB's 16.7% on sale price) is not the same as GC overhead on construction — that's an investment-margin calc, not a feasibility calc.

How accurate is this calculator's output?

Planning range, not contractor bid. Intended use: to decide whether a lot + build pencils before paying for soils reports, architectural drawings, and a builder walk-through. Per the methodology, no calculator can be more accurate than the soil conditions and utility tap location an operator hasn't observed yet — that's why the contingency band starts at 12% and the operator notes flag specific surprise lines (site-prep, foundation, kitchen-bath-finishes). Tighten by overriding individual lines after a soils report comes back or after a preliminary builder consultation.

What I’d do next

  1. Pair the cost with the schedule — construction timeline calc

    Same project decision has two halves: dollars and calendar. Run the timeline calc with matching inputs to surface the schedule horizon alongside this feasibility budget — and especially before flipping the OB toggle, where the calendar tradeoff is what the dollar savings really cost.

  2. Refine the foundation line — concrete yardage calc

    Foundation is always in scope on new-build. Drop into the concrete calc to size the footings + foundation walls + slab order, then come back and override the foundation line.

  3. Read the planning-range methodology

    What's anchored on NAHB 2024, what's a SiteworkMath calibration, and how the GC overhead vs NAHB sale-price-profit clarification works.

Also in this cluster


By James Wu. Planning-range methodology and per-cluster sourcing tiers in methodology. Per-sqft sanity-check anchor: NAHB 2024 Cost of Constructing a Home ($162.50/sqft average). Owner-builder slowdown anchored on US Census 2024 Survey of Construction (single-family build durations: contractor 12.1mo / owner-builder 15.2mo → 1.26x). NAHB 16.7% on sale price is referenced in methodology as a sanity check, NOT used as a constructive multiplier — GC overhead anchored on Chicago-metro residential industry typical 10–15% on hard costs. Engine logic in lib/sitework/projectcost/projectcost.ts; new-build catalog in line-items-newbuild.ts. Numbers are SiteworkMath planning ranges, not contractor bids — feasibility framing is part of the output for that reason. Not structural, financial, or legal advice. Full methodology.